Utilities works on Greenford Road, September 2023 to March 2024
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-17/08/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Greenford Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 24/09/2023
- Estimated End Date
- 18/03/2024
What we are doing
We will install a new gas main on Greenford Road from 24 September 2023 to 18 March 2024. This work is in preparation for our Tunnel Boring Machines to pass through the area. The junctions of Bennetts Avenue and Uneeda Drive on either side of Greenford Road will be closed there will be a temporary work site in this area. Clearly signposted diversion routes will be in place.
On Greenford Road traffic management with a lane closure and temporary traffic lights will be in place 24 hours a day throughout these works.
The working hours will be Monday to Friday 8am to 6pm and Saturdays 8am to 6pm. No noisy works will take place after 1pm on Saturdays. The works will pause on 4 December 2023 until Monday 8 January 2024 over the Christmas period.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]