Utilities Works, Traffic Management Changes and Tree Removal on Old Oak Common Lane

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-06-30-01-2024

Work Item Summary

Project Phase
Phase 1
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Trial Holes, Utility works / surveys
Estimated Start Date
16/02/2024
Estimated End Date
24/03/2024

What we are doing

Utilities Works North of Kildun Court

From 16 February to 24 March, there will be traffic management changes on Old Oak Common Lane. Essential utility works need to be conducted as part of the next phase of construction.

We will be using non-invasive techniques to create trial holes to assess the structure of existing underground pipework. These works are part of our programme to safely assess utilities on Old Oak Common Lane (see map on document attached for locations).

This activity will involve carrying out trial hole investigations close to Kildun Court for approximately five weeks during our core working hours between 8am to 6pm on Mondays to Fridays. During this time there will be a northbound lane closure on Old Oak Common Lane with two- way traffic lights and a designated temporary pedestrian crossing. These dates are subject to change, and we will keep the local community informed.

Tree removal North of Kildun Court

Around 26 February we will be removing a tree close to Kildun Court to allow us to safely carry out these vital utility works. Unfortunately, the tree is too close to the underground utility structures and will therefore need to be removed, so that the work can be carried out safely.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]