Utilities Works, Traffic Management Changes and Tree Removal on Old Oak Common Lane
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-06-30-01-2024
Work Item Summary
- Project Phase
- Phase 1
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Trial Holes, Utility works / surveys
- Estimated Start Date
- 16/02/2024
- Estimated End Date
- 24/03/2024
What we are doing
Utilities Works North of Kildun Court
From 16 February to 24 March, there will be traffic management changes on Old Oak Common Lane. Essential utility works need to be conducted as part of the next phase of construction.
We will be using non-invasive techniques to create trial holes to assess the structure of existing underground pipework. These works are part of our programme to safely assess utilities on Old Oak Common Lane (see map on document attached for locations).
This activity will involve carrying out trial hole investigations close to Kildun Court for approximately five weeks during our core working hours between 8am to 6pm on Mondays to Fridays. During this time there will be a northbound lane closure on Old Oak Common Lane with two- way traffic lights and a designated temporary pedestrian crossing. These dates are subject to change, and we will keep the local community informed.
Tree removal North of Kildun Court
Around 26 February we will be removing a tree close to Kildun Court to allow us to safely carry out these vital utility works. Unfortunately, the tree is too close to the underground utility structures and will therefore need to be removed, so that the work can be carried out safely.