Utility diversion works in Wells House Road
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-31-24/02/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane, Wells House Road
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Utility works / surveys, Vegetation clearance
- Estimated Start Date
- 13/05/2024
- Estimated End Date
- 31/05/2025
What we are doing
As we continue with the construction programme at Old Oak Common station site, we have a number of activities that will be taking place between now and November 2024.
Utility diversion works
To enable the construction of the new rail bridges into the future Old Oak Common Station, we need to divert an existing electrical power cables which is located behind properties on the south side of Wells House Road.
We will carry out these works in phases:
- Phase 1: Complete bat surveys and undertake vegetation removal and tree felling, May 2024– June 2024. For details, follow this notice.
- Phase 2: The temporary diversion works, June – November 2024.
- Phase 3: The permanent diversion of the new cable which will be positioned along the south side of Wells House Road, summer to autumn of 2025
For further details of above works please follow the link to the notification below.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]