Overnight emergency ground investigations on Western Avenue

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-20/01/23

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Western Avenue
Contractor
SCS JV
Type of works
Ground investigations
Estimated Start Date
06/02/2023
Estimated End Date
17/02/2023

What we are doing

From 6 February to 17 February 2023, we will be carrying out emergency cadent gas ground investigations on Western Avenue.

The ground investigations will take place between 10pm to 5am Monday to Friday to reduce the effect on road users. Two lanes will remain open to allow traffic to flow. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.

For further details please see notification below.