Utility Work Fazeley Street

Work item: HS2-EW-LM-Ph1-Bir-Cur-St-N4-UT-3-28/04/202

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Birmingham
Worksite Name
Curzon Station
Contractor
LM JV
Type of works
Utility works / surveys
Estimated Start Date
24/05/2021
Estimated End Date
20/12/2021

What we are doing

Over the coming months, we’ll continue to work on roads in central Birmingham as we carry out a programme of utility diversions and prepare for the construction of HS2’s Curzon Street Station and the railway. This involves Severn Trent Water works at the junction of New Canal Street and Fazeley Street

What to expect
A full closure of the junction of New Canal Street and Fazeley Street Core working hours are 8am to 6pm, although staff may be on site up to an hour before and an hour after those times. Traffic management measures will be in place beyond these times.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]