Utility works in Breakspear Road South, Hillingdon
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-UTs-3-14/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South
- Worksite Name
- Breakspear Road South
- Contractor
- Align JV, SSEN
- Type of works
- Utility works / surveys
- Estimated Start Date
- 02/04/2022
- Estimated End Date
- 14/04/2022
What we are doing
In order to construct the railway, we need to supply electricity to our compounds and work sites. In order to complete the cable connection works that are currently underway at Copthall Road West we need to install a larger high voltage cable from Copthall Road West across Breakspear Road South to connect with the existing substation. We expect these works to begin on Saturday 2 April 2022 and they will last until Thursday 14 April 2022 from 7am – 7 pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]