Utility works in Copthall Road West, Hillingdon
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-UTs-3-14/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Hillingdon
- Worksite Name
- Copthall
- Contractor
- Align JV, SSEN
- Type of works
- Utility works / surveys
- Estimated Start Date
- 21/03/2022
- Estimated End Date
- 02/05/2022
What we are doing
In order to construct the railway, we need to supply electricity to our compounds and work sites. SSEN will be working in your area to upgrade the local electricity network this will include trench excavation and cable laying in roadside verges in Copthall Road West. From 21 March 2022 – 2 May 2022 Monday – Friday 7.30 am – 17.30pm and Saturday 8am – 1pm