Utility Works in Duddeston

Work item: HS2-EW-UT-Ph1-Ar-No-N1-UT-20-16/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Birmingham, Duddeston
Worksite Name
Duddeston
Contractor
Severn Trent Water
Estimated Start Date
09/08/2021
Estimated End Date
30/04/2022

What we are doing

Severn Trent Water, working on behalf of HS2, need to carry out sewer diversion work in North Duddeston in an area adjacent to the existing railway line, to move a sewer out of the path of the new HS2 line. How will this impact you? This means that Severn Trent Water will be working in the area highlighted in blue on the image below. The construction work will include excavation and tunneling activities to ensure that the sewer is moved safely.

Work will start on 9th August 2021 through until April 2022

Core working hours will be 8.00am to 6.00pm (Mon-Fri) and 8.00am to 1.00pm (Sat)

There will be an increase in construction traffic as Severn Trent’s contractors, J Murphy and Sons set up site, mobilise equipment and materials and undertake the sewer diversion. Every endeavour will be made to keep disruption to a minimum.