Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Greenford Road
- Worksite Name
- Greenford
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 13/03/2023
- Estimated End Date
- 04/04/2023
What we are doing
We wrote to you last month regarding the utility works on Greenford Road to dig two trial holes which was planned to be completed on 24 March 2023. Due to a change in the work required for the second trial hole we have delayed this work.
We will now be digging the second trial hole on Greenford Road from 31 March to 4 April 2023 during the following times – Friday to Tuesday 8am to 6pm.
Traffic management with a reduction in lane width and additional traffic lights will be in place 24 hours a day during this time.
For further details please see update notification below.
Download information relating to these works
- Update on delayed utility works on Greenford Road, Ealing - 31 March to 4 April 2023