Utility works on Hampstead Road corner of Harrington Square

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Traf-1-01/06/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
19/06/2023
Estimated End Date
22/12/2023

What we are doing

We are currently installing a new cable route from Lidlington Place to Varndell Street via Granby Terrace, to replace the existing route on Hampstead Road.

On 19 June we will recommence utility works on Hampstead Road.

From 19 June to December there will be multiple lane closures on Hampstead Road, between Harrington Square and Granby Terrace. We will maintain one lane for northbound traffic and one lane for southbound traffic. Pedestrians will not be impacted by these works; the footpath and pedestrian crossings will be maintained.

You may notice periods of increased noise as we breakout and reinstate the road. We will use acoustic blankets where possible to limit noise.

For further details please see notification below.

Download information relating to these works