Utility works on Stanhope Street and Park Village East – completed

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog Works-1-07/03/24

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Park Village East, Stanhope Street
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
08/04/2024
Estimated End Date
17/05/2024

What we are doing

Update: We have completed our utility works on Stanhope Street and Park Village East a month ahead of schedule. Our utilities team worked efficiently to complete the works as quickly as possible to reduce impact to residents. Our temporary traffic management was removed on Friday 17 May and the southbound lane and footpath have now been reopened to the public.

We thank you for your patience while we carried out these essential works.

We are installing a new cable route from Lidlington Place to Varndell Street via Granby Terrace.

From 8 April, we were installing ducts in the road and footpath outside our site access gate at the junction of Stanhope Street and Park Village East.

To complete this work, we had to close the southbound lane and footpath with 2-way temporary traffic lights to control the flow of traffic with crossing points at either end of the work site to divert pedestrians to the opposite footpath.

Several parking bays on Stanhope Street have been suspended with parking bays remained open outside Cubitt Court.

For further details of above works please refer to page 3 in the notification below.