Utility works on Victoria Road, North Acton
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-01/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- London, Old Oak and North Acton
- Location
- Victoria Road
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 20/03/2023
- Estimated End Date
- 25/03/2023
What we are doing
From 20 to 25 March 2023, we will be carrying out a series of ground investigations on Victoria Road between the entrance and exit to Boden. The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction.
The ground investigations will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.
To ensure the safety of the public and our staff, temporary changes will be in place on Victoria Road. We will have a lane closure in place between the entrance and exit to Boden. Access to Boden will not be affected.
Download information relating to these works
Find out more about