Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Stanhope Street
- Contractor
- SCS JV
- Type of works
- Footpath closures, Lane closure, Utility Works
- Estimated Start Date
- 03/08/2025
- Estimated End Date
- 18/09/2025
What we are doing
We need to install UK Power Network (UKPN) ducts in the road and footpath outside our site access gate at the junction of Stanhope Street and Park Village East, opposite Cubitt Court.
We will begin works on Monday 4 August and expect to complete these by mid-September. We will set up the site area from 10pm on Sunday 3 August to begin works the following day.
We will also be working on the weekend of 9 and 10 August from 8am to 5pm on Saturday, and 10am to 4pm on Sunday. To reduce impacts to residents, there will be no breaking concrete after 1pm on Saturday and no noisy works on Sunday.