Utility works update – Calvert
Work item: FUS_AWN_0284 HS2-EW-Fusion -Ph1-Ar-Ce-C2-Traf-39-05/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Calvert
- Contractor
- Fusion JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 10/11/2021
- Estimated End Date
- 21/12/2021
What we are doing
Further to our last community notification in September 2021, we are writing to give you an update on the utility diversion works at Calvert Road and Brackley Lane, Calvert.
Our phase 3a works on Calvert Road are approaching completion with the closure of Calvert Road being removed on Tuesday 9 November. Thank you for your understanding during these works. We will have some final works to undertake in this area later in the programme – this will require traffic light control to complete. The phase 2 programme of drilling works has taken longer than expected due to a combination of wet weather and ground conditions. The remaining drilling works are programmed to be completed in December 2021.