Utility works update – Calvert

Work item: FUS_AWN_0284 HS2-EW-Fusion -Ph1-Ar-Ce-C2-Traf-39-05/11/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Calvert
Contractor
Fusion JV
Type of works
Utility works / surveys
Estimated Start Date
10/11/2021
Estimated End Date
21/12/2021

What we are doing

Further to our last community notification in September 2021, we are writing to give you an update on the utility diversion works at Calvert Road and Brackley Lane, Calvert.
Our phase 3a works on Calvert Road are approaching completion with the closure of Calvert Road being removed on Tuesday 9 November. Thank you for your understanding during these works. We will have some final works to undertake in this area later in the programme – this will require traffic light control to complete. The phase 2 programme of drilling works has taken longer than expected due to a combination of wet weather and ground conditions. The remaining drilling works are programmed to be completed in December 2021.