Vegetation clearance and borehole filling at Bridgwater Road playing field
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-OTH-1-13/6/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Bridgwater Road playing field
- Worksite Name
- South Ruislip
- Contractor
- SCS JV
- Type of works
- Borehole works, Vegetation clearance
- Estimated Start Date
- 29/06/2023
- Estimated End Date
- 04/07/2023
What we are doing
What we are doing
In advance of our TBMS passing through the Bridgwater Road playing field area, we will need to fill in some groundwater monitoring boreholes located in the overgrown area and at the edge of the Bridgwater Road playing field (see map overleaf).
In order to gain access to the area, we will need to cut back the brambles and weeds so that we can access the boreholes.
Concrete will be pumped into the borehole to seal it. We will need to return to the area on 4 July to top up the cement and clear the area.
We will also be filling in an additional borehole however this is located in an area that does not require vegetation clearance.
The playground will not be affected.