Vegetation clearance and UKPN Utility work

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-18-12/02/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Ground investigations, Traffic management
Estimated Start Date
26/02/2023
Estimated End Date
27/03/2024

What we are doing

We want to inform you that from 26 February we will be carrying out vegetation clearance on a section of Wormwood Scrubs, adjacent to Old Oak Common Lane. This area is being cleared so that UK Power Network (UKPN) can carry out vital cable diversions required for the construction of Old Oak Common Station. The clearance will include the removal of one tree and some shrubs that obstruct the cable route.

An ecological survey has been conducted, and an environmental officer will oversee the work to ensure environmental compliance.

From 27 February until 24 March, a southbound lane closure will be in place to allow UKPN to conduct trial hole surveys. These surveys will allow UKPN to assess the ground conditions so that cabling work can occur safely. UKPN have advised that they will operate temporary traffic lights in this area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]