Vegetation clearance – Birmingham Rd B4114

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-37-05/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Coleshill
Contractor
BBV JV
Type of works
Vegetation clearance
Estimated Start Date
23/05/2022
Estimated End Date
01/06/2022

What we are doing

BBV will be carrying out vegetation clearance around the Old Barn Guest House and Capitol Joinery sites off Birmingham Road. Vegetation will be cleared and chipped into a tractor and trailer to be removed from the sites. The workforce will access the site off Birmingham Road.

Download information relating to these works