Vegetation clearance, Quainton Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-38-23/07/2021| 1MC12-EKF-IN-NTE-CS08-000009
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- EKFB JV
- Type of works
- Vegetation clearance
- Estimated Start Date
- 14/10/2021
- Estimated End Date
- 21/10/2021
What we are doing
What are we doing?
As the project progresses, it is necessary to remove vegetation to enable future works to continue and to allow access to areas of the site. There will be a lane closure on Quainton Road for vegetation clearance works.
Why are we doing it?
In this instance we are clearing and preparing entry from Quainton Road onto the internal site access roads. The internal access roads are designed to carry construction traffic inside our work areas which means less vehicles travelling along the local road networks.
Further to these works, we will be creating the junctions and establishing the vehicle crossing points here and on Station Road at a later date.
When will these works take place?
Quainton Road will have a lane closure from Thursday 14 October to Thursday 21 October. We will work to open the roads to reduce disruption as soon as possible during our periods of working.
Works will take place between 8am and 6pm – Monday to Friday. Some additional weekend work may also take place.
Download information relating to these works