What we are doing

Ahead of the main construction works in the area of the A418, we need
to carry out some ecology surveys and vegetation / tree clearance along
the A418, Oxford Road in the area of the former Aylesbury golf course.
As some of these works will need to be carried out on or adjacent to the
carriageways in the area we will at times need to put in place two-way
temporary traffic management.
We will also need to remove trees alongside the southern verge of the
A418, opposite the former golf course. We will need a temporary
footpath closure to carry out these works safely.