Vegetation works Addison Road

Work item: AWN FUS_AWN_0212HS2-EW-Fusion -Ph1-Ar-Ce-C2-Eco-26-05/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Steeple Claydon
Contractor
Fusion JV
Type of works
Vegetation clearance
Estimated Start Date
17/05/2021
Estimated End Date
28/05/2021

What we are doing

Before the main railway construction works for the realignment and reconstruction of the new bridge commences on Addison Road, we need to carry out the removal of roadside hedgerows and vegetation clearance along the highway boundary. As some of these works will need to be carried out on or adjacent to the carriageway we will need to put in place temporary traffic lights between the hours of 9.30am and 3.30pm, the road will open as normal outside of these times.
The works will take place between Monday 17 May to Friday 28 May 2021 weekdays only.
Where appropriate some sections of vegetation will be replaced with temporary fencing, this will help keep the site secure ahead of future construction activities.