Victoria Road: Next phase of Tunnel Boring Machine power supply
Work item: HS2-MW-CSJV-Ph1-OOC-St-S4-Prog-works-21-25/04/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Road closure
- Estimated Start Date
- 26/04/2022
- Estimated End Date
- 27/04/2022
What we are doing
Tunnel Boring Machine power supply works
In July of last year, we wrote to you outlining our phased programme of works for the tunnel boring machine power supply along Victoria Road. The power supply works which started at Atlas Road roundabout junction with Victoria Road and progressed southbound along Victoria Road will now resume its final phases ahead of its completion date of Spring 2022.
Victoria Road (Near Vehicle Holding Area) 26 April – 27 April (8pm – 6am)
CSJV will continue with the power supply works along Victoria Road in the southbound and northbound carriageway. These works will be carried out on the evening of 26th April 2022. During this period, an Antiskid surface will be added to the existing road surface. The works will be conducted in two phases, as shown below in the traffic management diagrams. Two-way traffic lights will be in place to maintain traffic flow along Victoria Road. During these works, bus stops will be suspended
northbound and southbound as shown in the below traffic management plans. Where possible we will relocate suspended bus stops to a new temporary location close by, however it is not always possible due to the distance between stops and other highway restrictions.
Utility supplies and other services will not be affected by these works.
Virtual drop-in events in 2022
You can contact our local engagement team via the HS2 Helpdesk. We are also available to speak with you at monthly virtual one to ones in Old Oak and Park Royal on the following dates:
• Wednesday 27 April, 3pm to 6pm
• Wednesday 25 May, 3pm to 6pm
To register for the next drop-in, please visit www.hs2.org.uk/events/ If you are not able to attend the above virtual 1:1s please contact our local engagement team via the Helpdesk. We are happy to arrange a 1:1 with you at another time.