What we are doing
What we are doing
On the weekend of 24 and 25 July 2021, we will be carrying out utility installation works. We will be removing the road surface and excavating a trench to install cables and water pipes.
We will carry out the main cut into the concrete within normal working hours on Friday 23 July 8am to 6pm to minimise noise on the weekend. On Saturday 24 July and Sunday 25 July we will be working extended hours until 5pm. Once connected the trench will be backfilled and the work area reinstated, these activities should not cause any disruption.
These works will be confined to our site compound area, within the bell mouth where vehicles access the site from Harvil Road.
Your utility services will not be affected.