Weekend works to install tower crane

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-14/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Parkway
Contractor
SCS JV
Type of works
Enabling works
Estimated Start Date
15/04/2022
Estimated End Date
19/04/2022

What we are doing

Scaffold install during weekend working hours – 16 April

We will install a tower crane in Euston Throat worksite during the weekend 23 to 24 April (Tower Crane B). The tower crane will sit on top of a large frame, above our future haul route. For safety, we must install an anti-trespass scaffold around this base frame, before we install the tower crane.

For safety, we need to install this scaffold when there are no other works nearby. We will install the scaffold on Saturday 16 April during extended weekend working hours from 8am to 6pm, before we install the tower crane the following weekend. Our team will use hand tools to construct the scaffold and we do not expect these works to be noisy.

We will also be carrying out piling and surveys during extended working hours this weekend, from 15 to 19 April.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]