Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-09/02/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Westgate
Worksite Name
Westgate
Contractor
SCS JV
Type of works
Works Update
Estimated Start Date
15/02/2024
Estimated End Date
31/08/2024

What we are doing

From 15 February to 31 August 2024, we will be building the reinforced concrete headhouse structure within the Westgate site, situated between the River Brent and West Gate.

The concrete walls of this structure will be between 10 and 14 metres high.
Most of the works will be carried out during our core hours, but some will need to take place outside core hours for safety reasons.

During these works the following activities will be taking place:

  • Deliveries
  • Concrete works
  • Form works
  • Steel fixing