Wood End Lane traffic management
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-7-19/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Fradley, Wood End Lane
- Worksite Name
- Fradley, Wood End Lane
- Contractor
- BBV JV
- Type of works
- Haul road construction, Traffic management
- Estimated Start Date
- 28/02/2022
- Estimated End Date
- 22/04/2022
What we are doing
We will be installing temporary traffic lights and lane closures on Wood End Lane. This is to allow us to safely complete the construction of new junctions to connect our haul roads, minimising disruption where possible.
These works will take place in two locations along Wood End Lane, please see map.
• Location 1: From 28 February until 25 March.
• Location 2: From 28 March until 22 April.
Our working hours will be from 8:00am until 6:00pm Monday to Friday.
Access to properties will always be maintained. Our workforce can be on site one hour before and after to set up and secure our equipment.
Please be aware there are other contractors working within the area for three nights from 7 March until 10 March, carrying out survey work to investigate the location and condition of buried cables. You can check one.network for the latest information about traffic management in your area.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]