Work on A38 northbound slip road in Streethay
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-7-26/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Streethay
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 05/09/2022
- Estimated End Date
- 30/06/2023
What we are doing
We will be installing a 40mph speed limit and narrowing the lanes on the A38 northbound slip road. This is to enable us to divert utilities, which includes power, BT and Virgin Media.
When will the work take place
The narrower lanes will be in place 24 hours a day starting in September 2022 and ending in June 2023. There may be times throughout this work that we are able to remove the traffic management for periods of time.
Throughout these works, our working hours will be 8am until 6pm.