Works at Atlas Road site during Autumn 2022
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-09/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Estimated Start Date
- 25/08/2022
- Estimated End Date
- 31/10/2022
What we are doing
Ongoing works at Atlas Road site during Autumn 2022
We are continuing to prepare the Atlas Road site ready for the assembly and launch of the tunnel boring machine (TBM) and the construction of the Atlas Road logistics Tunnel (ARLT). The works which are planned for late Summer/Autumn 2022 include:
• Delivery of gantry crane elements*
• Assembly of Tunnel Boring Machine (TBM)*
• Completion of the launch ramp and box for the Atlas Road Logistics Tunnel, including excavations and steel works*
• Completion of the TBM workshop and commercial store
• Installation of site silos and grouting plant ahead of future construction
• Installation of electrical substations
• Installation of water treatment plant and water-cooling area
• Installation of on-site utilities connections
• Testing and commissioning of the conveyor system
*Some activities may require extended working hours. We will advise the community in advance of these works.
Additional information about the Atlas Road site and the Atlas Road Logistics Tunnel can be found at:
https://www.hs2.org.uk/wp-content/uploads/2022/07/2207-Atlas-Road-Logistics-tunnel-FAQs-final_.pdf
Dates and times mention in this notification may change – we will keep you updated vis post and at https://www.hs2.org.uk/in-your-area/map/