Skip to main page content
View route map

Works at Atlas Road site during Autumn 2022

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-09/08/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Worksite Name
Old Oak Common
Contractor
SCS JV
Estimated Start Date
25/08/2022
Estimated End Date
31/10/2022

What we are doing

Ongoing works at Atlas Road site during Autumn 2022

We are continuing to prepare the Atlas Road site ready for the assembly and launch of the tunnel boring machine (TBM) and the construction of the Atlas Road logistics Tunnel (ARLT). The works which are planned for late Summer/Autumn 2022 include:
• Delivery of gantry crane elements*
• Assembly of Tunnel Boring Machine (TBM)*
• Completion of the launch ramp and box for the Atlas Road Logistics Tunnel, including excavations and steel works*
• Completion of the TBM workshop and commercial store
• Installation of site silos and grouting plant ahead of future construction
• Installation of electrical substations
• Installation of water treatment plant and water-cooling area
• Installation of on-site utilities connections
• Testing and commissioning of the conveyor system

*Some activities may require extended working hours. We will advise the community in advance of these works.

Additional information about the Atlas Road site and the Atlas Road Logistics Tunnel can be found at:
https://www.hs2.org.uk/wp-content/uploads/2022/07/2207-Atlas-Road-Logistics-tunnel-FAQs-final_.pdf

Dates and times mention in this notification may change – we will keep you updated vis post and at https://www.hs2.org.uk/in-your-area/map/

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]