Works at Atlas Road site during summer 2022
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-19/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, Old Oak and North Acton
- Location
- Atlas Road
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Delivery of materials
- Estimated Start Date
- 19/05/2022
- Estimated End Date
- 31/08/2022
What we are doing
Ongoing works at Atlas Road site during summer 2022
We are continuing to prepare the Atlas Road site ready to build the Atlas Road Logistics Tunnel and install the conveyor system. Works planned at the Atlas Road site during summer 2022 include:
• Ground excavations, backfills and concrete pours
• Installation of on-site utilities connections
• Installation of silos and grouting plant ahead of future construction activities
• Construction of the launch ramp and box for the Atlas Road Logistics Tunnel including excavations, prefabricated steel reinforcements, concrete works and drainage
• Construction of tunnel boring machine (TBM) workshop
We held an online engagement event in March 2022 about ongoing and upcoming works at the Atlas Road site. You can view the presentation at www.https://www.hs2.org.uk/in-your-area/local-community-webpages/hs2-in-old-oak-and-north-acton/community-engagement/
Hoarding artwork update – Midland Terrace
Over the past year, we have been liaising with local representatives from Midland Terrace and Shaftesbury Gardens about hoarding artwork for the section of hoarding near the Dudding Hill railway bridge and the embankment area on Victoria Road. We will install ivy artwork on this section of the site hoardings. The artwork has now arrived on site. The installation dates for the artwork are being discussed with our Atlas Road site team. We will let you know when the hoarding artwork is planned to be installed.
Deliveries to Atlas Road site
During late May and June, we will receiving deliveries to the Atlas Road site in preparation for future works. Where possible, deliveries will take place during daytime hours. Some deliveries will take place overnight.
Speak to our local engagement team Our local engagement team are happy to speak with you in person or virtually about any questions you have about our works in your local area. To arrange a time to speak with us in person, please contact the HS2 Helpdesk. If you wish to speak with us virtually, please register for a 20-minute session during our next virtual one-to-ones at www.hs2.org.uk/events/
SCSJV will also be carrying out monthly pop ups on the third Wednesday of each month to speak with local residents in the area. These are to start in mid-June 2022. Further details including times and locations will be posted to the community shortly.