Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Park Village East
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- hydro-demolition
- Estimated Start Date
- 10/11/2025
- Estimated End Date
- 28/11/2025
What we are doing
Following our site safety stand down, we have now begun a safe restart of works across our sites in Euston Approaches Due to some overpoured concrete in Zone G within Camden Cutting north, we need to complete works to remove the excess material.
From Monday 10 November, we will begin a hydro-demolition process, which uses a high-powered water blaster to break up and remove the excess concrete. We anticipate we will need around three weeks to complete this process. There may be periods of noise while we use the water blaster, however these works will be within an acoustic tent to minimise noise to neighbouring properties. After the excess concrete has been removed, we will – dismantle the acoustic tent.
We will work from Monday to Friday during core hours, from 8am to 6pm.
We apologise for any inconvenience caused.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]