Works in Euston Approaches, January to summer 2024

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-12/12/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Granby Terrace bridge, Hampstead Road, Park Village East, Stanhope Street, Varndell Street
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Bridge works, Construction, Event, Lorry lay-by set-up, Road closure, Utility works / surveys
Estimated Start Date
02/01/2024
Estimated End Date
30/06/2024

What we are doing

Update regarding the Euston Portal Headhouse engagement events.

We previously informed you we will hold online and in-person engagement events to seek your views on the design of the Euston Portal Headhouse. Unfortunately, we need to reschedule these events. We will send out postcard invites with event dates and instructions on how to register in February.

Please see below the notification of works in Euston Approaches to take place from January to summer 2024 including;

  • No works over festive period  from 23 December to 1 January 2024
  • Euston Portal Headhouse design engagement events in winter and spring 2024
  • Utility works requiring road closure at the junction of Varndell Street and Stanhope Street, 2 January to April 2024
  • Utility works in Ampthil Estate – summer 2024
  • Ongoing works near Coniston and Cartmel until summer 2024
  • Mornington Street bridge reopening – January 2024
  • Cavern lorry lay-by extension – spring 2024
  • Granby Terrace bridge – new bridge deck installation from May 2024

 

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]