Works on A47 Heartlands Parkway – Birmingham
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-02-20/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Saltley
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 07/08/2023
- Estimated End Date
- 06/10/2023
What we are doing
A47 – Heartlands Parkway Survey Works
We will be carrying out a variety of surveys on A47 Heartlands Parkway between Saltley Viaduct roundabout to Aston Church Road roundabout from Monday 7 August for one week.
To complete these survey works, we will need to put lane closures in place between 9.30am and 4.00pm.
A47 – Heartlands Parkway Fencing Works
We will be carrying out some works to our site fencing between Aston Church Road onto A47 Heartlands Parkway from Monday 18 September for approximately three weeks. During this time, we will require a short lane and footpath closure between Aston Church Road roundabout onto A47 Heartlands Parkway between 9.30am – 4.00pm.
A47 – Heartlands Parkway/Saltley Viaduct – lane closures
We will be carrying out some utility works between Saltley Viaduct onto A47 Heartlands Parkway from Thursday 10 August for approximately three weeks. During this time, we will require a short lane closure between Saltley Viaduct roundabout onto A47 Heartlands Parkway 24/7.
The dates of our works are subject to change depending on ground and weather conditions. Access to all frontages will remain open as usual.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]