Works on Bangley Lane

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-2-14/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire
Location
Drayton Bassett, Hints
Contractor
BBV JV
Type of works
Construction, Traffic management
Estimated Start Date
19/04/2022
Estimated End Date
24/06/2022

What we are doing

To allow our vehicles to cross Bangley Lane and to maintain the safety of road users, equestrian and pedestrians, we will create a signalised plant crossing. To enable us to commence these works we will require a temporary closure of a section of Bangley Lane.

When these works will take place
We will complete these works in two phases of daytime and 24-hour closures of a section of Bangley Lane.
The first phase of works will take place from Tuesday 19 April to Friday 27 May. During these works we will install a temporary daytime closure of a section of Bangley Lane between 8.00am to 6.00pm.
Pedestrian and equestrian access will be maintained at all times.
The second phase of works will be completed from 1 June for 2 weeks. During these works we will install a temporary 24-hour closure of a section of Bangley Lane.
Pedestrian and equestrian access will NOT be maintained during this 2-week closure.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]