Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Drayton Bassett, Hints
- Contractor
- BBV JV
- Type of works
- Construction, Traffic management
- Estimated Start Date
- 19/04/2022
- Estimated End Date
- 24/06/2022
What we are doing
To allow our vehicles to cross Bangley Lane and to maintain the safety of road users, equestrian and pedestrians, we will create a signalised plant crossing. To enable us to commence these works we will require a temporary closure of a section of Bangley Lane.
When these works will take place
We will complete these works in two phases of daytime and 24-hour closures of a section of Bangley Lane.
The first phase of works will take place from Tuesday 19 April to Friday 27 May. During these works we will install a temporary daytime closure of a section of Bangley Lane between 8.00am to 6.00pm.
Pedestrian and equestrian access will be maintained at all times.
The second phase of works will be completed from 1 June for 2 weeks. During these works we will install a temporary 24-hour closure of a section of Bangley Lane.
Pedestrian and equestrian access will NOT be maintained during this 2-week closure.