Works on Eversholt Street (East of Euston Station)

Work item: HS2-MW-MD-Ph1-Eu-St-S3-CR-32-22/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden, Euston station, Eversholt Street
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
11/07/2022
Estimated End Date
01/02/2023

What we are doing

Works on Eversholt Street

From Mid July 2022 we will begin the sewer upgrade works, trial holes and telecoms. These works are necessary as we prepare for the HS2 Euston station. These works include lane closures – please see the attached document for full details.

To minimise disruption, we are undertaking works concurrently and in phases.

Download information relating to these works