Works on Hampstead Road

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-12-28/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Cardington Street, Hampstead Road, North Gower
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
01/08/2022
Estimated End Date
31/07/2023

What we are doing

Water main trial hole surveys on Hampstead Road

We have been carrying out utilities works to the west of Euston station. As part of this, we will be carrying out potable water trial hole surveys on Hampstead Road in August 2022.

 