UPDATE: Works on North Gower Street and Drummond Street
Work item: HS2-EW-CSJV-Ph1-Ca-S1-Prog-works-1-19/05/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Euston station
- Contractor
- CS JV
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 19/05/2021
- Estimated End Date
- 06/08/2021
What we are doing
From 24 May until 6 August 2021 utilities works for electrical power connections will take place in the road of Drummond Street and North Gower Street. Excavation and ducting work will be carried out in phases.
Parking and loading bays will be suspended. Pedestrian access will be maintained.
28 June 2021: Update – A full road closure of North Gower Street junction with Drummond Street has been put in place to enable the completion of Phase 3 of the works, which are due to be finished on 12 July. Access to Stephenson Way, Euston Street and North Gower Street will now be via the Euston Road slip.
For more information please see the updated June notification below.
Download information relating to these works
- North Gower Street and Drummond Street - May 2021
- North Gower Street and Drummond Street - June 2021 UPDATE
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]