Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Park Village East
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- Footpath closures
- Estimated Start Date
- 02/02/2026
- Estimated End Date
- 13/02/2026
What we are doing
We previously informed you that we need to identify the drainage holes in the Park Village East wall to ensure they are working correctly. In order to do this, we will be pouring water mixed with non-harmful drain tracing dye into the planter. These works started on Monday 2 February, however due to difficulties locating the drainage area within the planter, we will now continue these works during week commencing Monday 9 February.
If we encounter any further issues, we may need to work the following week as contingency, however we will aim to complete these works by Friday 13 February.
We will continue using equipment to remove material from the planter and maintain the parking bay suspensions and footpath closure opposite 22 to 26 Park Village East. There may be periods of increased noise, however we will use acoustic blankets to reduce impacts. We will work from Monday to Friday during core hours, from 8am to 6pm.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]