Excavating concrete at Mandeville Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-11/11/2024_1
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road worksite
- Contractor
- SCS JV
- Type of works
- Concrete break out
- Estimated Start Date
- 28/04/2025
- Estimated End Date
- 16/05/2025
What we are doing
We carried out excavating and breaking concrete 22 metres below ground in the Satellite Shaft from November until late March. Half of these works were completed, and the second half will take place from 28 April 2025 until 16 May 2025.
How this will affect you
The works will be carried out using an excavator and concrete breaker in the shaft. You may notice vibration and noise from the construction machinery. We will use noise reducing barriers to help keep noise and vibration to a minimum. We will work as efficiently as possible, while keeping our work areas safe and tidy.