Excavating concrete at Mandeville Road site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-11/11/2024_1

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Location
Mandeville Road
Worksite Name
Mandeville Road worksite
Contractor
SCS JV
Type of works
Concrete break out
Estimated Start Date
28/04/2025
Estimated End Date
16/05/2025

What we are doing

We carried out excavating and breaking concrete 22 metres below ground in the Satellite Shaft from November until late March. Half of these works were completed, and the second half will take place from 28 April 2025 until 16 May 2025.

How this will affect you

The works will be carried out using an excavator and concrete breaker in the shaft. You may notice vibration and noise from the construction machinery. We will use noise reducing barriers to help keep noise and vibration to a minimum. We will work as efficiently as possible, while keeping our work areas safe and tidy.