Works to Guinness Bridge and Piccadilly Line Overbridge on Western Avenue
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Tun-1-24/10/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- A40, Western Avenue
- Worksite Name
- Guiness Bridge, Western Avenue
- Contractor
- SCS JV
- Type of works
- Protection Works
- Estimated Start Date
- 15/11/2023
- Estimated End Date
- 14/01/2024
What we are doing
From 30 October 2023 to 30 June 2024 we will be carrying out works to protect the Guiness Bridge and Piccadilly Line Overbridge on Western Avenue.
The works will take place between 7am and 7pm Monday to Sunday.
Traffic management will be in place 24 hours. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.
The works will involve putting up scaffolding, jacking the bridge and replacing bearings and bearing plates ahead of the Tunnel Boring Machines (TBM) passing this area.
To ensure the safety of the public and our staff, temporary changes will be in place on Guinness Bridge including lane closure and pedestrian diversion. Two-way traffic flow will be maintained. No traffic management will be required in relation to the Piccadilly Line Overbridge.
For further details please see notification below.