Works to Stanhope Street site access gate
Work item: HS2-MW-SCS-Ph1-Eu-St-S3-CR-48-11/04/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Stanhope Street
- Contractor
- SCS JV
- Type of works
- Traffic management, Worksite / compound set-up
- Estimated Start Date
- 22/11/2021
- Estimated End Date
- 26/11/2021
What we are doing
Footway closure on Stanhope Street – 22-26 November
- From 22 November, we will carry out works to widen the Stanhope Street site access gate.
- We will work from within site to replace the existing gate with a bigger model and reposition the hoarding around it.
- The section of footway in front of the gate will be closed
Hoarding and fencing works on Stanhope Street – 29 November to late-December
- From 29 November, we will replace a section of hoarding between Stanhope Street and Langdale footpath with fire-proof hoarding.
- We will require a lane and footway closure at the northern end of Stanhope Street, temporary traffic signals will be in place.
- The Langdale footpath between Stanhope Street and Harrington Street will be closed from 6 December for two weeks while we replace the fence. The works may be noisy, and we will surround the working area with acoustic barriers.
For details of above works please see notifications below.
Download information relating to these works
- Hoarding and fencing works on Stanhope Street – 29 November to late-December
- Footway closure on Stanhope Street - 22-26 November