Works to the West and East of Euston Station
Work item: HS2-EW-MD-Ph1-Eu-St-S3-Site-11-20/04/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden
- Contractor
- Mace Dragados JV
- Type of works
- Ground investigations, Utility works / surveys
- Estimated Start Date
- 04/05/2021
- Estimated End Date
- 31/12/2021
What we are doing
Ground investigation and trial holes until December 2021
We are progressing ground investigations at Euston Road and Doric Way and beginning trial holes at various locations – at the east side of Euston Square Gardens, Melton St, Cobourg St, Euston St, North Gower St, former Maria Fidelis school site and Hampstead Rd.
Hoardings installation and refurbishment until August 2021
We have begun works to widen the pedestrian walkway along the Drummond Street corridor, and we will replace the existing hoardings and lighting, including installing new graphics and planters on the junction of Cobourg Street.
Relocation of London Underground (LU) Traction Substation (TSS), enabling works April – mid June
To facilitate the construction of the proposed HS2 station we will relocate the current London Underground vent shaft and substation at Melton Street to a new site at Wolfson site (formerly Wolfson House). Site enabling works will begin end April 2021 for approximately six weeks and the main construction works will continue until 2024.
Pile cropping (trimming) & upper wall construction west of Euston station, April – October 2021
We are continuing piling activities to construct an upper wall, which will extend the previously installed western basement retaining wall at the former National Temperance Hospital site.
Download information relating to these works