Work item: HS2-EW-MD-Ph1-Eu-St-S3-Site-11-20/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Contractor
Mace Dragados JV
Type of works
Ground investigations, Utility works / surveys
Estimated Start Date
04/05/2021
Estimated End Date
31/12/2021

What we are doing

Ground investigation and trial holes until December 2021

We are progressing ground investigations at Euston Road and Doric Way and beginning trial holes at various locations – at the east side of Euston Square Gardens, Melton St, Cobourg St, Euston St, North Gower St, former Maria Fidelis school site and Hampstead Rd.

Hoardings installation and refurbishment until August 2021

We have begun works to widen the pedestrian walkway along the Drummond Street corridor, and we will replace the existing hoardings and lighting, including installing new graphics and planters on the junction of Cobourg Street.

Relocation of London Underground (LU) Traction Substation (TSS), enabling works April – mid June

To facilitate the construction of the proposed HS2 station we will relocate the current London Underground vent shaft and substation at Melton Street to a new site at Wolfson site (formerly Wolfson House). Site enabling works will begin end April 2021 for approximately six weeks and the main construction works will continue until 2024.

Pile cropping (trimming) & upper wall construction west of Euston station, April – October 2021

We are continuing piling activities to construct an upper wall, which will extend the previously installed western basement retaining wall at the former National Temperance Hospital site.