West of Euston works including Drummond Street

Work item: HS2-EWCSJV-Ph1-Eu-St-S3-OTH-15-12/06/2020

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden, Euston station
Contractor
CS JV, Mace Dragados JV
Type of works
Ground investigations, Utility works / surveys
Estimated Start Date
04/01/2021
Estimated End Date
14/10/2021

What we are doing

The programme of utility works to the west side of Euston Station includes the laying of electrical power connection ducts and BT telecommunication,
Virgin Media and Vodafone ducts via North Gower Street across Euston Road, Gower Street and Gower Place finishing at Gordon Street.

We also need to carry out sewer construction, diversion and disconnection works in number of streets including Stephenson Way, Euston Street, Regnart Buildings, Drummond Street and Cobourg Street.

Latest update:

  • Regnart Buildings – the road is closed until end July 2021.
  • Stephenson Way – a section of the road at the end furthest from North Gower Street is closed to vehicles until mid June 2021.
  • Euston Road/Gower Street – now open, works completed.
  • Gower Place and Gordon Street – works will complete by 25 July.
  • Drummond Street/North Gower Street – electrical power connections work in phases from 24 May until 6 August 2021.

Further details can be found in May notifications below.