West of Euston works including Drummond Street
Work item: HS2-EWCSJV-Ph1-Eu-St-S3-OTH-15-12/06/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Camden, Euston station
- Contractor
- CS JV, Mace Dragados JV
- Type of works
- Ground investigations, Utility works / surveys
- Estimated Start Date
- 04/01/2021
- Estimated End Date
- 14/10/2021
What we are doing
The programme of utility works to the west side of Euston Station includes the laying of electrical power connection ducts and BT telecommunication,
Virgin Media and Vodafone ducts via North Gower Street across Euston Road, Gower Street and Gower Place finishing at Gordon Street.
We also need to carry out sewer construction, diversion and disconnection works in number of streets including Stephenson Way, Euston Street, Regnart Buildings, Drummond Street and Cobourg Street.
Latest update:
- Regnart Buildings – the road is closed until end July 2021.
- Stephenson Way – a section of the road at the end furthest from North Gower Street is closed to vehicles until mid June 2021.
- Euston Road/Gower Street – now open, works completed.
- Gower Place and Gordon Street – works will complete by 25 July.
- Drummond Street/North Gower Street – electrical power connections work in phases from 24 May until 6 August 2021.
Further details can be found in May notifications below.
Download information relating to these works
- May update of utility works on Euston Road, Gower Street, Gower Place, Gordon Street
- May update of utility works on North Gower Street and Drummond Street
- Update of utility works on Gower Street, Gower Place and Euston Road - April 2021
- West of Euston utilities works notice: December 2020
- West of Euston utility works map: March 2021
- West of Euston utility works lookahead: March 2021
- Drummond Street road diversion guide week commencing 22 March 2021
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]