Work items found 5053

A list of current and past work items for the HS2 project.
Name Status Location Estimated Start Date Estimated End Date
Notice of Ellesborough Road lane closure for utility works Completed

Ellesborough Road

28/02/2024

22/03/2024

Notice of new road layout, Greatworth temporary road Current

Greatworth

29/02/2024

01/03/2027

Notice of overnight road closures, A43, Brackley BP roundabout to the Syresham junction Completed

A43

11/03/2024

15/03/2024

Notice of emergency overnight lane closure– A452 slip road – Marston Green Completed

Marston Green

04/03/2024

05/03/2024

Traffic management in Gilson near Water Orton Completed

Gilson

11/03/2024

05/04/2024

Notice of Utility Construction Works Moorhall Farm/Grand Union Canal Completed

Moorhall Road

11/03/2024

24/05/2024

Northolt Tunnel East Newsletter February 2024 Completed

Northolt

22/02/2024

31/05/2024

Notice of piling works at Copthall tunnel site Completed

Copthall Gate 2

11/03/2024

30/06/2024

Notice of extension to Ellesborough Road closure for temporary realignment tie-in Completed

Ellesborough Road

24/02/2024

28/02/2024

Borehole filling near Wilsmere Drive, Northolt Completed

Wilsmere Drive

04/03/2024

08/03/2024

Notice of footpath closure Waddesdon Greenway Completed

Waddesdon

11/03/2024

14/03/2024

Notice of sewer lining works on School Road Completed

School Road

04/03/2024

11/03/2024

Notice of 24-hour works at South Ruislip Vent Shaft Site Completed

South Ruislip

04/03/2024

02/08/2024

Notice of borehole removal, site entrance, Mandeville Road Vent Shaft Completed

Mandeville Road

11/03/2024

15/03/2024

Common Lane – early morning construction activity Completed

Common Lane

26/02/2024

26/02/2024

Notice of daytime lane closure A413 London Road, Wendover Completed

A413

07/03/2024

15/04/2024

Notice of lane closure, A418 Completed

A418

07/03/2024

08/03/2024

Update: Vegetation clearance works on West Gate Completed

A40, Western Avenue, Westgate

27/02/2024

28/02/2024

Notice of weekend working at Canterbury Works site Completed

Canterbury Works

02/03/2024

17/03/2024

Update: Westgate Headhouse concrete structure Completed

West Gate

15/02/2024

31/08/2024