Work items found 4955

A list of current and past work items for the HS2 project.
Name Status Location Estimated Start Date Estimated End Date
Network Rail works over Easter period at the Euston Station and Clarkson Row Completed

Clarkson Row, Euston station

07/04/2023

11/04/2023

Network Rail works over Easter period at the Euston Station Completed

Clarkson Row, Euston station

07/04/2023

11/04/2023

Notice of road closure; Ridgeway Lane near Ufton Completed

Ufton

15/05/2023

17/05/2023

Notice of traffic management on A446, Watton Lane and Gorsey Lane, Coleshill Completed

Coleshill

17/04/2023

30/06/2023

Updated notice of road closure, Rugby Road, Cubbington Completed

Cubbington

24/04/2023

20/05/2023

Notice of extended working hours in Water Orton, Gilson and Coleshill Completed

Coleshill, Gilson, Water Orton

18/04/2023

29/09/2023

Updated notice of temporary traffic lights on B4455, Fosse Way Completed

Offchurch

26/04/2023

28/04/2023

Easter weekend working at Mandeville Road site Completed

Mandeville Road

07/04/2023

10/04/2023

Update on Utilities works on Station Approach and Long Drive, April 2023 Completed

South Ruislip

15/04/2023

14/05/2023

Notice of ground investigation surveys, Hamley Heath Completed

B5013, Hamley Heath

17/04/2023

12/05/2023

Overnight utilities work on Oldfield Lane North, Greenford Completed

Oldfield Lane North

11/04/2023

10/05/2023

Spring 2023 update: Canterbury Works Ventilation Shaft Completed

Canterbury Works, Kilburn

16/03/2023

31/05/2023

Update on Tunnel Boring Machine material storage Completed

Hillingdon

13/04/2023

31/05/2023

HS2 Works Notification: Traffic management, A41 Completed

A41, Waddesdon

21/04/2023

21/04/2023

Notice of temporary traffic lights on the A525, and the A51 junction, Woore Completed

A51 Junction, A525

11/04/2023

21/04/2023

Notice of road closure on the Beaconside area, Stafford Completed

A513, A513 Beaconside, Hydrant Way, Stafford, Weston Road

11/04/2023

26/04/2023

HS2 Works Notification: Road Closure, Shipton Lee Road, Quainton Completed

Quainton

11/04/2023

21/04/2023

Update of daytime temporary traffic lights on the A515, B5014 and the A513, Kings Bromley Completed

A513, A515, B5014

27/03/2023

07/04/2023

Ground investigation works opposite 22-24 Park Village East postponed to 24 April – 5 May Completed

Park Village East north

31/03/2023

28/04/2023

Works over Easter weekend in Euston Approaches – 7 to 11 April Completed

07/04/2023

11/04/2023