Name Status Location Estimated Start Date Estimated End Date
Notice of Footway Closure on Old Oak Common Lane Completed

Old Oak Common lane

15/12/2021

15/12/2021

Notice of ground investigation survey work, Great Haywood Completed

Tolldish Lane

29/11/2021

19/01/2022

Notice of ground investigation survey work, Moss Lane Completed

Moss Lane

29/11/2021

20/01/2022

Notice of surveys on Checkley Lane and Den Lane Completed

Checkley Lane

14/12/2021

15/12/2021

Notice of surveys on A51, Dog Lane and Bent Lane Completed

A51

14/12/2021

14/12/2021

Notice of surveys on Chorlton Lane, Casey Lane and Weston Lane Completed

Chorlton Lane

14/12/2021

15/12/2021

Extended closure of Welsh Road, Offchurch Completed

Offchurch

03/12/2021

31/01/2022

Notice of construction of concrete reinforced piers – Curzon Street Completed

Birmingham, Curzon Street

04/01/2021

31/12/2022

Notice of road closure St James Place and Viaduct Street Completed

Birmingham

04/01/2021

31/07/2024

Traffic Management on Diddington Lane Completed

Hampton in Arden

10/01/2022

28/01/2022

Notice of minor watercourse surveys near A513 and Shaw Lane Completed

Lichfield

13/12/2021

16/12/2021

Notice of minor watercourse surveys near Snape Hall Road Completed

Whitmore

13/12/2021

16/12/2021

Notice of minor watercourse surveys near Yarnfield Lane and Eccleshall Road Completed

Yarnfield

13/12/2021

16/12/2021

Notice of minor watercourse surveys near M6 Completed

Yarnfield

13/12/2021

16/12/2021

Temporary, overnight lane closures along the M42 and exit slip road closure off the M6 junction 4 from Wednesday 15 December to Thursday 16 December Completed

Chelmsley Wood, Coleshill

15/12/2021

16/12/2021

Notice of tower installation for the conveyor Completed

Adelaide Road

13/12/2021

05/02/2022

Notice of minor watercourse surveys near Hoo Mill Lane Completed

Great Haywood

13/12/2021

16/12/2021

Notice of vegetation clearance at South Ruislip ventilation shaft site Completed

South Ruislip

11/12/2021

29/01/2022

Update notice of construction at South Ruislip ventilation shaft site Completed

South Ruislip

03/12/2021

04/06/2022

Notice of single lane closure on Faraday Avenue / Hams Lane Completed

Hams Hall

10/01/2022

28/01/2022