Indirect contract opportunities
We publish information on key awarded tier 2 subcontracts within our supply chain and encourage interested suppliers to get in touch using the contact details provided.
We also publish details of live and upcoming subcontract procurements to be undertaken by our tier 1 contractors, to provide early visibility of opportunities to the market.
Apply for live indirect contract opportunities on CompeteFor
Downloadable tier 2 awarded contracts AND tier 1 contractor procurement pipeline
Indirect contracts found 1840
| Tier 2 Contractor | Tier 2 Package | Tier 2 Package Value | Contact email for procurement enquiries |
|---|---|---|---|
| MINEARC SYSTEMS | TBM Toilet Block | £0m - £1m | [email protected] |
| MineArc Europe LTD | Service and Maintenace of TBM Refuge Chambers | £0m - £1m | [email protected] |
| Millennium Personnel Services Ltd | PSV - Specialist labor for swivel crane operation | £1m - £10m | [email protected] |
| Millcroft Services PLC | Scaffolding (Area Central) | £0m - £1m | [email protected] |
| MIDLAND DESIGN GROUP | CAD Support | £0m - £1m | |
| MHTECH ENERGIES LTD | Decarbonisation report | £0m - £1m | [email protected] |
| MGF TRENCH CONSTRUCTION SYSTEMS | Utility Bridge | £0m - £1m | [email protected] |
| Meridian Energy Consulting Limited | Utilities Lloyds NERS Technical Support and Assessment | £0m - £1m | [email protected] |
| McNealy Brown Limited | Metalwork - West Ruislip Attentuation Tank Package Order | £0m - £1m | [email protected] |
| McManus Projects and Developments Limited | TBM Labour Fitters (Area West) | £1m - £10m | [email protected] |
| McManus Projects and Developments Limited | Invert Concrete and Drainage Labour | £1m - £10m | [email protected] |
| McManus Projects and Developments Limited | Permenant Walkways (NTE and NTW) - Labour and Formwork | £10m - £50m | [email protected] |
| McGinley Support Services Infrastructure Limited | Labour Supply | £1m - £10m | [email protected] |
| McGinley Support Services (Infrastructure) Limited | Construction Labour Supply | £50m - £100m | [email protected] |
| MCGINLEY SUPPORT SERVICES | Labour (Above) Ground | £10m - £50m | [email protected] [email protected] |
| McGee Group Holdings Ltd | Exhumations Cardington Street | £1m - £10m | |
| MCFOUR | A5 Temp road diversions - Drainage | £0m - £1m | [email protected] |
| MCDERMOTT BUILDING AND CIVIL ENGINEERING | Remaining Trace Drainage Packages (6no Assets) | £0m - £1m | [email protected] [email protected] |
| MCDERMOTT BUILDING AND CIVIL ENGINEERING | BROT IS - External works - Groundworks (Drainage, Ducting, Substructure, Paving, Kerbs and associated Earthworks)) | £1m - £10m | [email protected] [email protected] |
| MCDERMOTT BUILDING AND CIVIL ENGINEERING | Steel Fixing - SD-RW - Attleboro Assets | £1m - £10m | [email protected] [email protected] |
| MCDERMOTT BUILDING AND CIVIL ENGINEERING | Drainage for Earthworks | £10m - £50m | [email protected] [email protected] |
| MCDERMOTT BUILDING AND CIVIL ENGINEERING | Steel fixing - SD/RW - Self Delivery and Retaining Wall – Birmingham Spur Dive Under | £10m - £50m | [email protected] [email protected] |
| McDermott Building & Civil Engineering Ltd | Land Drainage Works | £0m - £1m | [email protected] |
| MCCALLS SPECIAL PRODUCTS LTD T/A MACALLOY | PSV - Temporary PT | £1m - £10m | [email protected] |
| McAuliffe Civil Engineerin Ltd | Remediation/removal of asbestos | £0m - £1m | [email protected] |
| McAllister Bros Limited | Post TBM Utility CCTV Surveys | £0m - £1m | [email protected] |
| McAllister Bros Limited | WP026.5.1 Utilities Design and Build - Sewer Lining - Area Central Lot 1 - Stage 1 Design and Construction Readiness | £1m - £10m | [email protected] |
| McAllister Bros Limited | WP026.5.3 Utilities Design and Build - Sewer Lining - Area Central Lot 3 - Stage 1 Design and Construction Readiness | £1m - £10m | [email protected] |
| McAllister Bros Limited | WP026.5.2 Utilities Design and Build - Sewer Lining - Area Central Lot 2 - Stage 1 Design and Construction Readiness | £1m - £10m | [email protected] |
| Maylarch Environmental Ltd | Demolition of existing buildings including surveys and asbestos removal within T2G. | £0m - £1m | [email protected] & [email protected] & [email protected] |
| Maxwell Geosystems UK Limited | Mission OS Surveying Licence | £1m - £10m | [email protected] |
| Maxwell Geosystems UK Limited | Mission OS Surveying Licence | £0m - £1m | |
| MAXWELL GEOSYSTEMS UK | I&M Software & Database | £0m - £1m | [email protected] |
| MAWSLEY MACHINERY | MEWP | £0m - £1m | [email protected] |
| MAWSLEY MACHINERY | Telehandlers Phase 2 | £1m - £10m | [email protected] |
| Maurer (UK) Limited | Design, Supply and installation of Expansion Joints for the 5 viaducts | £0m - £1m | [email protected] |
| MATRIX BOOKING | Desk & Car Park Allocation System | £0m - £1m | |
| Matiere UK Limited | Installation of Green Tunnels Incl Insitu Works | £50m - £100m | [email protected] |
| Matiere SAS | Providing Professional and Specialist Knowledge in preparation of proposals for supply and installation of Green Tunnel PCC sections, waterproofing and associated works. | £0m - £1m | [email protected] |
| MASON STREET FURNITURE | National Highways Billboards | £0m - £1m | [email protected] [email protected] |
| MASON STREET FURNITURE | Supply & Installation of Traffic signs & Street Lighting works including Street Lighting Survey & Street Furniture Removal | £0m - £1m | [email protected] [email protected] |
| MASON STREET FURNITURE | Saltley Street Furniture Works | £0m - £1m | [email protected] [email protected] |
| MARUBENI-KOMATSU | Earthworks Equipment Investment No2 - Excavators, Dozers and ADTs | £1m - £10m | [email protected] |
| MARUBENI-KOMATSU | Komatsu - Repairs & Maitnenance | £1m - £10m | [email protected] |
| MARUBENI-KOMATSU | Earthworks Equipment Investment Phase 3: Excavators & Dozers | £1m - £10m | [email protected] |
| MARUBENI-KOMATSU | Earthworks Equipment (Purchase) | £10m - £50m | [email protected] |
| Martifer UK Ltd | GWML Station Structural Steel Frame | £10m - £50m | [email protected] |
| MARTIFER UK | Structural Steel - Composite Beams (Package 2.1 - Main Subcontract) | £50m - £100m | [email protected] |
| MARTIFER UK | Structural Steel - Composite Beams (Package 2.1 - Limited PSC - 3 months) | £0m - £1m | [email protected] |
| Marr Contracting | Lifting & Tower Crane Hirer - Heavy Cranes | £1m - £10m | [email protected] |