Indirect contracts found 1840
| Tier 2 Contractor | Tier 2 Package | Tier 2 Package Value | Contact email for procurement enquiries |
|---|---|---|---|
| Clancy Docwra Limited | WP026.2 - Thames Water Critical Assets - Lining - Design and Build | £10m - £50m | [email protected] |
| Clancy Docwra Limited | WP026.1 (A&B) - Utility D&B - ACW - Hampstead Road Bridge (A) and Parkway (B) – Stage 1A Trial Holes and Surveys | £0m - £1m | [email protected] |
| Clancy Docwra Limited | WP026.1 (D) - Utility D&B - ACW - Park Village East – Stage 2 Construction | £0m - £1m | [email protected] |
| CLARANET | Microsoft and Tech Infrastructure Reseller | £1m - £10m | [email protected] |
| CLARITY HEALTHCARE | Occupational Health - Interim Solution | £0m - £1m | [email protected] |
| Clarke Demolition Company Ltd | Demolition of Small Dean Network Rail bridge | £0m - £1m | [email protected] & [email protected] |
| CLD FENCING SYSTEMS | Bromford East Tunnel Compound - Fencing | £0m - £1m | [email protected] |
| CLD Fencing Systems Limited | Security Gate and Fencing - South Ruislip Vent Shaft | £0m - £1m | [email protected] |
| Clean Your Site.Com Limited | Site Cleaning (Area Central) | £1m - £10m | |
| Clean Your Site.Com Limited | Site Cleaning (Area West) | £1m - £10m | |
| CLEVELAND CABLE | Bromford Temporary Tunnel Lighting System - Cable | £0m - £1m | [email protected] |
| CLIMB GLOBAL SOLUTIONS LTD (T.A Grey Matter Ltd) | Bing Maps API | £0m - £1m | [email protected] |
| Clipfine Ltd | Security & Logistics | £10m - £50m | [email protected] |
| Clipfine Ltd | Logistics and Security | £10m - £50m | |
| CMF Ltd | HS2 Scenic Lifts Envelope | £1m - £10m | Tim Wilford - [email protected] |
| CMT Equipment Limited | The Supplier to support the construction activities in respect to the provision of a wide range of site consumables for the supply and delivery, to service across all five sections of the project. | £1m - £10m | [email protected] |
| Coffey Geotechnics Limited | Geotechnical Support ( Area West) | £0m - £1m | [email protected] |
| COFFRAGE&QUIPAGE | PSV - Piers formworks and platforms | £0m - £1m | [email protected] |
| COFFRAGE&QUIPAGE | PSV_SoW_Superstructure formworks | £0m - £1m | [email protected] |
| COFFRAGE&QUIPAGE | PSV – Pier head platforms for deck stage | £1m - £10m | [email protected] |
| COFFRAGE&QUIPAGE | PSV - Lateral platforms for stay storage | £1m - £10m | [email protected] |
| COLAS | Minor works surfacing - temporary | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | LIW South SB3 Marquee and civils (Covid requirements) | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | BE STP Earthworks | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | Soil Stabilisation to Sub Lot 8.2 including Haul Road and Pile Mat | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | SL 8.2 Soil Stabilisation Streethay (Central & North) | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | BROT East Car Park Extension | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | Import of Material from external source | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | Transport of shield elements to Germany | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | Material Crushing | £0m - £1m | [email protected] |
| COLLINS EARTHWORKS | Earthworks Package 2B3 | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | WWH Bentonite Plant & others | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | Marston Box Enabling Works | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | Site Compounds (WWH) | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | BROM East Earthworks and Civils (S1/4) | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | LIW Earthworks | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | LIW Earthworks | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | LIW South Portal Earthworks | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | Backfill Package 1 (Carol Green, M191 & Canley Brook) | £1m - £10m | [email protected] |
| COLLINS EARTHWORKS | Bulk Earthworks - 2B | £50m - £100m | [email protected] |
| COLLIS ENGINEERING | LIW TBM launch fabrication | £0m - £1m | [email protected] |
| COLLIS ENGINEERING | Bromford East TBM Launch Steelwork | £0m - £1m | [email protected] |
| COLLIS ENGINEERING | Bromford Cross Passage Platforms & Ramps | £0m - £1m | [email protected] |
| COMBINED SOIL STABILISATION | Lime stabilisation and ground improvement | £0m - £1m | [email protected] |
| COMBISAFE | WWH Retained Cut Scaffolding | £0m - £1m | [email protected] |
| COMETTO | Supply of Self Propelled Modular Transporters | £1m - £10m | [email protected] |
| COMOL5 VOF | LIW & Brom TBM pipework & ancilliaries | £1m - £10m | |
| CONCEPT ENGINEERING CONSULTANTS | I&M Drilling & Installation | £0m - £1m | [email protected] |
| Concept Engineering Consultants Limited | Ground Investigation Works | £1m - £10m | |
| Concept Engineering Consultants Limited | Ground Investigation Works | £1m - £10m |