Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Crane installation
- Estimated Start Date
- 06/07/2026
- Estimated End Date
- 17/09/2026
What we are doing
We are beginning to remobilise the site to restart construction works following the safe stop of all construction activities on our site.
Initial work will involve using a crane to facilitate steel beam installations within the ventilation shaft.
From 6 July to 17 September 2026, SCS JV will install a crane on site to undertake works within the structure of the ventilation shaft.
These works will take place during the hours of 8am to 6pm Monday to Friday and 8am to 1pm Saturdays.
During this period, you may notice increased site activity and noise associated with these works.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]