Go to content
View all work items

A452 Kenilworth Road – roundabout construction (Phase 6)

Work item: HS2-EW-LM-Ph1-Ar-No-N1-Traf-4-06/01/2021

Work Item Summary

Project Phase
Phase 1
Region
Coventry
Location
Berkswell
Worksite Name
A452 Kenilworth Road
Contractor
LM JV
Type of works
Early construction works, Road closure
Estimated Start Date
14/06/2021
Estimated End Date
30/06/2021

Work item details

As previously notified, LM will soon restart works for the construction of the roundabout on the A452 Kenilworth Road, Berkswell, close to Park Lane.

What to expect

14 June – 15 June: Overnight road closure on the northbound carriageway 8:00pm to 6:00am to install barriers. Local access for residents and businesses via Beefeater roundabout.
15 June – 16 June: Overnight road closure on the southbound carriageway 8:00pm – 6:00am to install barriers. Local access for residents and businesses via Aston Martin roundabout.
29 June – 30 June: Overnight road closure on the northbound carriageway 9:00pm to 2:00am to swap the lane closure, followed by a short closure on the southbound carriageway for up-to one hour to install additional barriers.

16 June until further notice: Single lane closures on both carriageways 24/7. Traffic management including all signage will be erected as and when required subject to consent, site and weather conditions. Dates also subject to change.

Download information relating to these works

We'd like your feedback

Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]