Barrier installation on A404 Amersham Road and Whielden Lane, Amersham

Work item: HS2-ALIGN-26-2106

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Amersham, Amersham Road, Whielden Lane
Worksite Name
A404 Amersham
Contractor
Align JV
Type of works
Vehicle Restraint installation
Estimated Start Date
17/08/2026
Estimated End Date
21/08/2026

What we are doing

We will work alongside the highway to remove existing site hoarding and to install a new Vehicle Restraint System (VRS) around the Amersham Vent Shaft site on Whielden Lane and the A404, Amersham.

These safety barriers are designed to protect road users and the shaft site in the event of accidental collision.

Location
A404 Amersham Road and Whielden Lane boundary of Amersham vent shaft, Amersham

Duration
Works will take place over 3 weeks from Monday 17 August to Sunday 6 September 2026.

What to expect
There will be lane narrowing along the carriageway to create a safe working zone for operatives, particularly during busier periods.

We will make every effort to keep disruption to a minimum during this period.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]