Skip to main page content
View In Your Area map

Hampstead Road works

Work item: HS2-EW-SCS-Ph1-Ca-S1-Traf-47-17/05/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Contractor
CS JV, SCS JV
Type of works
Traffic management, Utility works / surveys, Worksite / compound set-up
Estimated Start Date
01/05/2021
Estimated End Date
31/08/2021

What we are doing

We are pleased to say, following community feedback, we now have agreement with Transport for London to create a right turn out of our Hampstead Road worksite gate. The right turn means lorries can avoid using Harrington Square as a turning loop to head south to Euston Road. To create this right turn, we will remove the central reservation Hampstead Road in three phases.

SCS works to remove Hampstead Road central reserve – 2 July to 30 August

  • Northbound lane will remain closed until 30 August due to the TW repair works
  • Traffic diversion to the southbound lane with two-way traffic lights.
  • Southbound bus lane and bus stop W suspended.
  • Junction of Varndell Street and Hampstead Road is closed until 12 August due to the sewer pipeline installation works carried out by CSjv
  • From 12 August Varndell Street will be access only from Hampstead Road.

CSjv sewer pipeline installation across Hampstead Road – due to complete by 12 August

Please see latest update notification below.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]